October 15, 2026
Two construction projects are changing the shoreline of Detroit Lake at once, and they won't finish together. The West Lake Drive and City Beach rebuild is in its last phases, and every remaining piece is scheduled to wrap up by the end of October 2026. The new Detroit Lake Pavilion is a different story. Foundation work started only in mid-September, and the city's current schedule doesn't open the building to events until June 2028. The finished beach walk could reach its first full summer more than a year before the building at the center of the waterfront has its first event.
The fastest progress has come on the road. Lakes Area Radio reported that West Lake Drive from Legion Road to Rossman Avenue reopened to traffic on September 4, about three weeks ahead of schedule. Crews then moved to the section between Rossman Avenue and Minnesota Avenue. That stretch is closed to through traffic, and work is expected to continue through the end of October.
The city's project construction schedule, updated October 5, shows exactly what's left. Every date on it is marked tentative and depends on weather and actual construction progress.
| Piece of the project | Status as of October 5, 2026 | Tentative dates |
|---|---|---|
| Street phase 1, Minnesota Ave to S. Washington Ave, plus the parking area between Lake Ave and S. Washington Ave | Complete | |
| Street phase 2, Legion Rd to Rossman Ave | Complete | |
| Street phase 3, Rossman Ave to Minnesota St | Underway | Sept. 8 to Oct. 30 |
| Beach phases 1 to 3: beach walk, lakeside plazas, Lake Ave plaza, plazas between Legion Rd and Rossman Ave | Complete | |
| Beach phase 4: Rossman Avenue boat launch reconstruction | Underway | Sept. 8 to Oct. 23 |
| Beach phase 5: new plazas at Summit Ave and Minnesota Ave | Underway | Sept. 21 to Oct. 30 |
| Beach phase 6: J&K Marina improvements | Upcoming | Late October |
The street phases do more than repave the road. Each one rebuilds the storm sewer and improves the stormwater treatment system, and phase 3 also replaces watermain. Each phase also extends the new multi-use trail, which is why the late-October finish matters to people on foot as much as to drivers. When phase 3 is done, the trail should run unbroken through the full corridor, which the city defines as Legion Road to Washington Avenue.
You don't have to wait for October 30 to use most of the new waterfront. According to the city's access notice, people on foot and on bikes can travel through the project corridor on the new multi-use trail, the beach walk, or both. The beach walk closes only temporarily around the two plaza work areas. All of the sand beach is open. During the boat launch and Summit and Minnesota plaza work, the turf beside the sand stays open too, apart from the sections under construction.
When the beach walk was first going in, the Detroit Lakes Tribune described it in late May as a six-foot walk, largely complete, with plaza foundations underway. In its September 9 update, Lakes Area Radio said crews would begin adding amenities to the completed sections, including benches, picnic tables, outdoor showers, drinking fountains and trash receptacles.
The city's schedule states that the beach and all businesses along the corridor stay open throughout construction, though access may shift as work moves from phase to phase. That covers the two restaurants most closely tied to this stretch of shore. Zorbaz Detroit Lakez at 402 W Lake Drive lists daily hours of 11 a.m. to 2 a.m. Lakeside Tavern & Brewery, which calls itself a City Beach staple, is listed at 200 West Lake Drive. If you're planning a late-season visit, check current hours with either one directly, since neither has posted fall or winter hours.
The boat launch matters most to anyone who still has a boat in the water. The Rossman Avenue launch is the piece being rebuilt right now, with a tentative finish of October 23, and the J&K Marina improvements are slated for late October.
A few blocks east of the beach work, the waterfront's best-known building is gone. The Tribune reported that demolition began on June 24, 2026, when heavy equipment started on the north wall of the 111-year-old building, built in 1915. Its last scheduled event was a community farewell on October 11, 2025, almost exactly a year before this fall's beach work wraps up.
In June the Tribune cited the city's target of finishing the new building in fall 2027. That date has since been replaced. At the August 26, 2026 City Council update, the construction manager McGough presented these milestones:
The presentation notes that these dates depend on subcontractor bidding and an amendment still to come, so they could change again.
Here is what the two timelines mean together. If the beach schedule holds, summer 2027 will be the first full season with every new plaza, the full beach walk and the rebuilt launch open. Steel for the new Pavilion is scheduled to start going up that March. Next summer's beach will be finished, with the Pavilion site still under construction next to it.
October is a milestone for the Pavilion as well, just a financial one. The August update scheduled McGough to finalize the guaranteed maximum price for the third bid package in mid to late October.
The estimate has already grown. On February 5, 2026, total project costs stood at $17,559,971 against a $17,300,000 budget. By August 25, 2026, the total was $19,732,961, an increase of $2,172,990. Much of that growth came from features added since schematic design. The list includes $329,000 in splash pad enhancements and $314,000 to put audio-visual systems in the construction budget. It also moved the boardwalk south of the Pavilion and the Park Lake Boulevard improvements from optional extras into the base bid.
The council presentation laid out three ways to pay for it. Local sales tax covers the largest share, $17.3 million in every version. A food and beverage tax adds $688,406, and the rest comes from a bond premium, a geothermal tax credit, park dedication funds, and possibly naming rights or sponsorships.
The design priorities in the same update describe what that money is meant to buy:
Four-sided Pavilion... Reactivating Beach Front at City Park... Event Hall Opens to Detroit Lake... Strategic Cues from Existing Pavilion
The update calls for a building meant to be seen from the north, south, east and west, with a multi-use bathhouse that also serves as the backdrop for an event lawn. Some pieces are still unfunded. A playground valued at $380,000 to $684,000 and improvements to the bandshell are listed as later master-plan work.
The 2026–27 winter will be the first since demolition, and the season's anchor events are planned away from the Pavilion site. Visit Detroit Lakes lists the Festival of Trees for Friday, November 20, 2026, at the Holiday Inn, with a dinner and auction. The Holiday Inn Detroit Lakes–Lakefront sits on the water at 1155 Hwy 10 East.
Polar Fest is set for February, but its organizers haven't posted 2027 dates yet. Their annual lineup includes the Polar Fest Plunge, Poles 'N Holes, the Ultra Snowmobile Rally, Frozen Fireworks and Cool Kites. Those dates, along with the October 23 and October 30 finish dates on the beach schedule, will show whether the waterfront ends 2026 on time.